On August 9, the Harrisville Fire District in its monthly meeting will discuss how to respond to Invenergy’s request for the supply of water for its proposed power plant in Burrillville, the Clear River Energy Center (CREC). For time and place follow this link.

Screen Shot 2016-08-08 at 9.47.53 PMFuture water shortages caused by CREC have been a topic of discussion and speculation for many months.  That indeed there is a serious risk is clear from information contained in documents obtained from several Rhode Island departments in response to Fossil Free RI‘s request made under the Access to Public Records Act.

As a reminder, the following is worth quoting from a previous post based on documents supplied by the RI Department of Health:

According to a presentation at a meeting about CREC attended by several state agencies, 0.18 MGD (million of gallons of water per day) will be left for growth if the power plant is built. June Swallow of the Center for Drinking Water Quality at the Rhode Island Department of Health attended the meeting. Her longhand notes show that Harrisville and Pascoag each are expected to need 0.12 MGD for growth. This suggests a deficit of 0.24 MGD – 0.18 MGD = 0.06 MGD.

Also documents supplied by the RI Department of Environmental Management raise concern. There is, for example, the following email exchange between Alisa Richardson of RIDEM and Ken Burke formerly of the Rhode Island Water Resources Board:

Thanks Alisa,
I think we should talk about having the Town acknowledge that with low flow conditions and high energy demands, that the Town is effectively pledging most (if not all) of its available water to this development. This local decision is theirs to make. Will someone from the Town also be at this meeting?
Thank you,
Kenneth J. Burke, P.E.MBA
General Manager/Treasurer

This email (my emphasis) appears on page 50 of this document.  There is more of interest, but the conclusion is the same; search the document for “Alisa” and “Ken.”

Also Stephanie Sloman, a retired environmental engineer who worked for a large electroplating plant in Massachusetts, weighed in. She submitted a thorough and detailed testimony to the Invenergy docket of the Energy Facility Siting Board.

Her conclusion is that, no matter how you look at it, there is not enough water for future growth in Burrillville and the other towns that draw from the same source.

Clearly, the RI departments of Environmental Management and Health, and the Water Resources Board are aware of the looming water supply problem. As Stephanie Sloman explains, anyone capable of elementary arithmetic can check this. As she points out, Invenergy is apparently is not one of those.

Recently, Gina Raimondo mentioned that she would withdraw her support for the CREC project if there were any issues. Of course, trouble with the water supply is only one of a myriad of issues each single one of which should suffice for her to make good on that promise.

Invenergy’s Niland pitches power plant at country club


Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387
John Niland
John Niland

John Niland, Invenergy’s director of development, gave a short presentation and answered eight questions at the Northern Rhode Island Chamber of Commerce’s Eggs & Issues Breakfast  Thursday morning. The questions were submitted in writing and carefully vetted before being read to Niland. The event was sponsored by the Clear River Energy Center, so there was little expectation of any kind of robust give and take. Held at the exclusive Kirkbrae Country Club, it wasn’t the venue for tough questions.

In attendance at this breakfast was Woonsocket Mayor Lisa Baldelli-Hunt, and state representatives Michael Marcello and Brian Newberry.

Niland has been Invenergy’s front man for a proposed fracked gas and diesel oil burning power plant in Burrillville. His messaging is always very careful and measured. Still, over the course of his short talk, he did reveal some interesting nuggets of information.

DSC_1682The proposed power plant is dual fuel, so it can burn either gas or oil. Though gas is not a clean energy source, it is better than burning oil for the environment directly surrounding the plant. The circumstances under which oil will be burned, then, is of some importance. Niland said, “some people are saying we will be making an economic choice” as to which fuel to burn when. [In fact, I was the first to suggest this, back in January.]

Niland did not dispute this analysis, per se, but said instead that the last time oil and gas were at price parity was in 2014, and indicated that it would therefor not be a problem.

He seems to think that oil’s current price of around three and four times that of gas is a permanent condition, ignoring the possibility of the gas bubble bursting (as I pointed out here) or that oil will collapse in price due to competition from renewables.

Niland also said that entering the ISO Forward Capacity Auction “was a risk for [Invenergy].” As I pointed out here, Invenergy’s proposed plant’s performance in the Forward capacity Market demonstrates that the plant is not needed. The ISO, a market that determines future energy prices here in New England, bought some power from Invenergy, but all the power it bought is surplus.

DSC_1703
Lorraine Savard

Niland completely reverses this analysis. Committing to purchasing some of the power from the proposed plant, he says, is the ISO’s “way of saying,’we need this power.’”

Not quite.

As for the water that Invenergy hopes to draw from a MTBE contaminated well and clean before dumping it as wast water in the Clear River, Niland admits that his company can “probably” clean the water and that they are “currently working up a detailed design” for the water treatment. MTBE is responsible for the closing of wells in Burrillville and has been linked to a terrible cancer cluster.

During the question and answer period Niland seemed pleased that Rhode Island has an Energy Facility Siting Board. Many states lack such a board, and he seemed to like having to deal with a state level agency made to smooth the way for power plant projects.

As for noise levels for the standard operation of the plant, Niland called the 43 decibels currently on the books in Burrillville “somewhat restrictive” and said that his company will ask for a variance.

Some curious math was proposed by Niland, who said that the plant, if approved, will begin construction “around this time next year, (May 2017) and be completed in 30-36 months, opening in June 2019. Not to be a stickler, but that’s 25 months for construction. We know that rushing construction leads to problems, is that what we’re heading for here?

Patreon

Burrillville Town Council claims to be powerless against Spectra, Invenergy


Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

20151014_190328More than 50 people packed the Burrillville Town Council chamber to register their objection to the Spectra energy pipeline expansion and the new $700 million “Clear River” methane power plant that’s proposed for Wallum Lake Road by Invenergy. Kathy Martley, of Burrillville Against Spectra Expansion (BASE), presented the town council with research she had gathered outlining the health risks and dangers of pipelines and power plants in the community.

Council President John Pacheco III and the other councilors did not seem very receptive to the concerns of the citizens in attendance. In response to questions raised at previous meetings about half the town council recently toured the Spectra plant and examined the work being done on the pipeline. They left satisfied that the pipes were not corroding and that the noise levels were within acceptable limits.

One town councilor said that during the tour they were told that Spectra was digging up some pipelines, so the noise was louder than usual. She seemed surprised that those in attendance laughed. But it was less funny when the town council revealed that all the information they have on Spectra’s actions and all the information they have on safety and public health issues comes from Spectra, and there are no other sources of information available.

“We have no legal authority to regulate or look at their reports,” said Pacheco, “We have to rely on Spectra.”

20151014_193020This was the refrain of the Burrillville Town Council throughout the meeting. Only FERC (the Federal Energy Regulatory Agency) can regulate Spectra, claims the town council. Spectra doesn’t even have to obey the town’s noise ordinances. “We don’t have control over Spectra and we can’t enforce local ordinances” against them, said Town Councilor David Place.

Meanwhile the vibrations from the pipeline compressors are so overpowering that plates rattle in the cabinets of Kathy Sherman’s home, who lives across the street from Spectra, she said. She warned the town council that there may be dire impacts on Burrillville due to Spectra’s expansion that have nothing to do with health or the environment.

“When you have people leaving, not paying their taxes, you will suffer for that,” she said.

Said Kathy Martley of BASE, “The value of this town is going into the toilet. I urge you to pass a resolution to oppose this power plant.” The crowd overwhelmingly agreed, applauding and cheering Martley’s words. But the town council seemed unwilling to be moved by their voters.

“FERC and the governor have all the power,” says Councilor Nancy Binns, “we don’t.”

Several times Council President Pacheco tried to close off comment, and several times those in attendance had to insist on being heard. “Why don’t we get to vote on this?” asked a man at the back of the crowd, “Newport votes on gambling over and over again, but we just have to accept this?”

Gina Raimondo

Instead of addressing the man’s concerns, Councilor Stephen Rawson insisted that discussing the new power plant would be illegal, since it’s not on the agenda, only the pipeline expansion is. This was news to Kathy Martley of BASE, who told me after the meeting that she’s pretty sure she asked that both items be on tonight’s docket.

Spectra held an open meeting recently in Burrillville. Residents were annoyed that “union people” holding signs in support of Spectra arrived early and took up all the parking spaces at the too small venue. Others complain that they don’t get proper notification about meetings from Spectra.

“Don’t you get notification of meetings?” asks a councilor.

“NO!” shouts virtually everyone in frustration.

“We asked about their notification process,” says Councilor Donald Fox, “they admitted that they aren’t as good as they used to be.”

Meanwhile, says Kathy Sherman, “No one from Spectra will return calls.”

The Town Councilors don’t want to be discussing this. They claim to be powerless in the face of Spectra. They recommend contacting Governor Gina Raimondo or State Representative Cale Keable. A man behind me says, referring to Keable, “He’s useless.”

Burrillville is home to two interstate methane gas pipelines, two methane gas compressor stations and the Ocean State power plant. Spectra Energy’s compressor station is already being expanded and a second expansion has been proposed. The proposed “Clear River” power plant plans to use Pascoag’s MBTE (methyl tert-butyl ether) tainted water supply for cooling.

In their press release, BASE suggested three things the town council could do in opposition to new methane energy infrastructure:

-Invenergy, the company that wants to build the plant, will try to negotiate with the town for a lower tax rate. If the Town refuses to negotiate with Invenergy and refuses to give them a tax break, the plant won’t be built.

-The Town will be asked by State agencies to submit official opinions about the power plant. If the Town Council says that they are against the plant, the State permits might not get approved.

-The power plant would need huge amounts of water to operate. The town has some power to deny Invenergy access to the local water supply and the pipes that will be needed to transport the water.

Amanda, another member of BASE, wants to know what the town council has done to move Burrillville towards a renewable energy future. After a few minutes of prevaricating, Councilor David Place is forced to admit that they’ve done almost nothing.

Invenergy also builds renewable energy power plants says Amanda, before demanding that the town council tell Invenergy to, “go solar or go home!”

After public comment on the subject is finally closed, and the citizens leave the building and gather outside on the sidewalk, no one seems happy with the performance of the town council. There is anger and frustration and talk of electing town councilors willing to stand with them against Spectra and Invenergy.

“When I started this two years ago, they could ignore me,” says Kathy Martley, of BASE, “They can’t ignore us any more.”