Updated: No LNG in PVD demands National Grid halt construction at Fields Point


Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

Fields Point Construction 04

The No LNG in PVD coalition is demanding that National Grid immediately halt construction and excavation work at 642 Allens Ave, the site of the proposed liquefaction facility in Fields Point. The proposed facility, which is opposed by Mayor Jorge Elorza and nine state legislators, is currently being reviewed by the Federal Energy Regulatory Commission (FERC). National Grid has requested that FERC not hold any public hearings or grant fast tracked approval for the project. No LNG in PVD, a coalition of residents, organizations, and elected officials opposed to National Grid’s LNG facility, calls on the RI Department of Environmental Management (RIDEM) to revoke a recently granted permit which authorized soil excavation at the site, which is contaminated with numerous toxins hazardous to human health.

Fields Point Construction 03A group of concerned Providence community members submitted a petition to RIDEM on August 31st which requested that RIDEM revoke the soil management permit until concerns are addressed and a Public Involvement Plan (PIP) is put in place. RIDEM site remediation regulations, amended in 2011, require a PIP – a formal process for public participation and community oversight of the cleanup plan for activities that occur on contaminated sites. RIDEM formally initiated the PIP on September 6th, notifying National Grid “to initiate the process of developing an approvable PIP associated with the planned environmental cleanup of the Providence Gas Company site, and any other site redevelopment activities requiring remedial actions that fall under the jurisdiction of the Remediation Regulations.”

National Grid was required to respond to RIDEM within seven days with proposed plans and a schedule for developing a PIP with the community, writes No LNG in PVD, but says National Grid has ignored this requirement. In addition to violating this regulatory request, says No LNG in PVD, National Grid has begun excavating soil in a large portion of the site along Allens Ave and Terminal Road. Community members have observed uncovered piles of dirt with visible airborne dust.

Fields Point Construction 02The project’s location, 642 Allens Ave, has a long history of industrial contamination dating back to the earliest days of the gas industry. Providence Gas Company operated a “manufactured gas plant” from 1910 to 1954 which resulted in the release of many toxic substances which polluted the soil and groundwater. The site has also been host to an ammonia plant, a toluene facility, a propane works, and most recently an LNG storage facility. Numerous substances which pose a risk to public health, safety, and the environment have been recorded at the site, including polycyclic aromatic hydrocarbons (PAHs), total petroleum hydrocarbons (TPH), phenolic compounds, volatile organic compounds (VOCs) including benzene and naphthalene, polychlorinated biphenyls (PCBs), ferri­ and ferro cyanide compounds, asbestos, and metals including lead and arsenic. Many locations in the site contain multiple hazardous substances at levels that far exceed allowed standards, and while some specific areas have been remediated since 1994, the majority of the land has not been remediated.

The petition submitted to to RIDEM articulated a number of community concerns about construction at the LNG site exposing workers or community members to toxins.

Fields Point Construction 01“This is our community, people live here and kids go to school here, why does National Grid think it’s okay to put our lives and our health at risk? It’s our legal right to be involved in these decisions,” said Gina Rodríguez, a community resident and leader in the No LNG in PVD coalition. Monica Huertas, another coalition leader said, “It’s outrageous that there’s a known toxic site this close to my house, and we can go down Allens Ave and see clouds of dust blowing off from the piles that National Grid is digging up. The whole point of this Public Involvement Plan law is to address things like that, but National Grid is just ignoring our concerns and DEM isn’t doing anything to stop them.”

A growing number of elected officials are working with the No LNG in PVD coalition and have declared opposition to National Grid’s unnecessary, expensive, and dangerous LNG proposal. The coalition denounces National Grid’s rush to begin work at the site before any public oversight is put in place. “This is exactly what RIDEM’s site remediation regulations are for,” said Representative Joseph Almeida. “In cases like this, where a project could release extremely dangerous contaminants, it is vital that the affected community have a role in overseeing remediation activities. Members of my district are already overburdened by environmental and health hazards. It is vital that DEM stop National Grid from kicking up a new load of previously buried poisons and toxics without giving this community any say.”

David Graves, spokesperson for National Grid, responded. “Construction work now underway on the property is not related to the liquefaction project. All of the work has been properly permitted. As part of our normal procedures, the earth excavated from the site is being covered.

“There are or will soon be two projects underway in the immediate area. One is construction of an access road to accommodate equipment that will come on site to make improvements to containment dyke wall that surrounds the LNG tank. The other is to cap approximately five acres of land at 642 Allens Ave that is part of a remediation project that was started several years ago. Both have been approved by DEM.”

No LNG in PVD coalition member Aaron Jaehnig responded to Graves’ statement. “The petition to DEM for a Public Involvement Plan related to that property clearly requested a halt to any construction or remediation projects until a Plan was in place. DEM’s request to National Grid, for that plan did not alter our request or sepcify that prior permits were exempt. The PIP process exists so the concerned residents, potentially effected by the disruption of toxic materials, are legally granted oversight to such projects. Its great that that National Grid believes they are above participation in this process, it just confirms our suspicions that their actions do not take the public’s well being into consideration. They have already shown a blatant disregard for the community by ignoring DEM’s request for response to the PIP order within seven days. All construction and remediation activity should be halted immediately until that process is completed.”

National Grid has responded a second time, denying some of the allegations made by the N o LNG in PVD coalition: “The work underway at our property at 642 Allens Ave. property, which has been properly permitted, is unrelated to the liquefaction project. One element of the work is environmental remediation. It is enhancing public safety not endangering it as claimed by one group. Also, at no time have we requested to FERC that they not hold public hearings and we responded to DEM on the matter of the Public Involvement Plan (which is unrelated to the current work on the property) within the required time. Every project we undertake is planned and executed under rigid safety and environmental standards and the work currently underway is no exception.”

Save The Bay wants Invenergy to prove consistency with Resilient RI


Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

save the bay logoIn a carefully worded press release, Save The Bay, one of Rhode Island’s premiere environmental advocacy groups, said, “it would be premature for the RI Energy Facility Siting Board (EFSB) to make a decision on a proposed natural gas-fired power plant in Burrillville before the state adopts a greenhouse gas reduction strategy.”

“Under the Resilient RI Act of 2014, the Executive Climate Change Coordinating Council (EC4) is required to submit to the Governor and General Assembly a strategy for achieving greenhouse gas emission (GHG) targets set forth in the Act. The deadline for this report is December 31, 2016. Until this strategy has been developed and adopted and the Invenergy proposal is shown to be consistent with the GHG reduction goals of the Resilient RI Act, it is premature for the RI Energy Facility Siting Board to issue a decision on Invenergy’s proposed power plant,” said Save the Bay Executive Director Jonathan Stone.

“Save The Bay expects the EC4 to consider carefully and thoughtfully a number of important questions in charting the state’s energy course. Among them: benefits and impacts of investments in renewable energy generation and energy conservation on energy system supply, distribution and reliability; the role of hydroelectric power in replacing nuclear power as part of the region’s energy mix; and whether or not the power generation capacity of the proposed facility is needed.

“Climate change is caused by the burning of fossil fuels and poses profound threats to the health and resilience of Narragansett Bay,” said Stone. “The pace of climate change is expected to accelerate. Already, rising sea levels are degrading the health of coastal wetlands, worsening coastal erosion and threatening public access along the shore. Warming temperatures contribute to harmful algal blooms, low oxygen levels in the Bay, and the loss of native species.”

If the Invenergy project moves forward and specific site plans and required permit applications are submitted to the RI Department of Environmental Management, Save The Bay will evaluate the proposed plant’s impacts on water quality, wetlands, and habitat conditions, in keeping with its role as steward of Narragansett Bay.

[Note: an earlier version of this piece was released with an incorrect Save the Bay logo.]

 

On Burrillville power plant, Janet Coit shows concern for the environment and/or future lawsuits


Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

DSC_3258The June 2 open meeting of the Energy Facilities Siting Board (EFSB) was a rare opportunity to hear board members Margaret Curran, Janet Coit and Parag Agrawal talk openly about their thoughts regarding the process of the board in approving or denying Invenergy‘s proposed fracked gas and diesel oil burning power plant in Burrillville. That said, it’s also a bad idea to draw too many inferences about board members thoughts based on their words.

One example of this came near the end of the 45 minute meeting. Janet Coit, who directs the RI Department of Environmental Management (RIDEM) when she’s not on the EFSB, suggested directing RIDEM to expand their advisory opinions on the environmental impact to include impact on wetlands, impact on state conservation areas and the cumulative impact of all fossil fuel development in the area, including pipeline compressors and the Ocean State Power Plant.

Janet Coit
Janet Coit

It would be easy to see Coit’s suggestion, which was approved unanimously by the board, as indicative of a concern about environmental impacts and as a response to the concerns of community members who have spoken at one or more of the open comment hearings held in Burrillville. But Coit’s suggestion may be no more than an attempt to make sure all the bases are covered. Getting advisory impact statements does not take away the EFSB’s ability to rubber stamp the power plant. It just provides the board with appropriate legal cover.

Chair Curran was on board with the suggestion that the cumulative effects the fossil fuel infrastructure in Burrillville might have on wildlife, saying, “I’m partial to the bats.” But again, her concern for the bats might dissipate in the light of Invenergy’s desire to build a new power plant where it is not wanted.

Meg Curran
Margaret Curran

Coit also suggested that the EFSB take “official notice” of the court order that closed the MTBE contaminated well in Pascoag, the same well that Invenergy hopes to use to cool their turbines on the promise of cleaning up the contamination. The well was sealed after many families became due to the MTBE in their water. As a result of Coit’s suggestion the court order has become part of the official record.

There were no public comments allowed at this meeting, and no lawyers from any of the intervenors were allowed to ask questions or comment. The meeting was for the three board members to “discuss, deliberate and decide” on various aspects of the hearing process. They started by denying one “late intervention” of an abutting property owner and approving another. The difference between the two applicants seemed to be that one applicant was zoned for residential and business, a special case that may require a separate lawyer.

Parag Agrawal
Parag Agrawal

Todd Bianco, coordinator of the EFSB, ran through the current status of the advisory opinions the board has requested. Most of the opinions seem to be roughly on schedule. Surprisingly, Invenergy has yet to apply for the proper permits from the RI Department of Transportation (RIDOT). Under current rules, it would take RIDOT three months to process the applications, and Bianco said RIDOT was “unable to determine if the applications will be on time.”

The meeting ended with a discussion of how to do better outreach with the public. Bianco said that he continues to run advertisements for meetings in the ProJo and in two local Burrillville publications. This lead to a discussion of whether or not to have a Twitter account for the EFSB.

“It would be my first,” said Bianco, “I could learn how to tweet, and hashtags are a thing…”

John Niland
John Niland

DSC_3225

Patreon

2016 Rhode Island Compost Conference and Trade Show announces line up


Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

Deprecated: Function get_magic_quotes_gpc() is deprecated in /hermes/bosnacweb08/bosnacweb08bf/b1577/ipg.rifuturecom/RIFutureNew/wp-includes/formatting.php on line 4387

ecriThe 2016 Rhode Island Compost Conference and Trade Show will be held on Thursday, March 10 from 9 to 3 in the Student Union at Rhode Island College in Providence.  The conference is annually organized by the Compost Initiative of the Environment Council of Rhode Island, and this year is being held in partnership with the Office of Sustainability of Rhode Island College.

As the wave of the Green Economy washes over Rhode island and the planet,  composting food scrap is often the odd man out after solar energy and storm water management.  But creating a compost industry needs to be front and center in the Green Economy as it is part of both healing ecosystems and providing new resources for the economy.  Creating and using compost reduces trash, stores carbon in the soil, reduces runoff, and improves the size and quality of the food supply, while offering jobs in the places in RI that could really use them.

The way Rhode Island deals with food scrap is changing.  The organics collection law passed in 2014 has taken effect, and with facilities coming on line to compost and digest the food scrap, New regulations are going into effect that will boost the development of community and neighborhood composting..  The annual compost conference is the best place to learn about what is going on and to connect to the people making it happen.

This year the keynoter will be Michael Bradlee of Earth Appliance.  Bradlee is a long time composter and compost bin innovator and will talk about his work with the pilot compost project in Providence, his data on  how much compost you can get from food scrap, and where he thinks the industry is going on Rhode Island. Bradlee’s talk will be particularly informative for school, Community Gardens and Urban Farms.

Workshop presenters include:

  • Richard Pederson, the longtime City Farm Steward for Southside Community Land Trust, will be speaking on Urban Agriculture Composting
  • Waylon Pleasanton of Sustainable Generation, was the Facilities Operations Supervisor for the Delaware Solid Waste Authority’s Cherry Island facility and now works with Sustainable Generations customers to get operations up and running.  He will discuss “Lessons Learned in a Food Waste Composting Operation.”
  • Marissa Desautel is an environmental attorney who will explain Rhode Island’s new compost law and regulations.
  • A new Vermiculture cooperative, the Rhody Worms Cooperative is getting off the ground. Monique Bosch and Bob Barnes will lead the discussion about what they are doing and how you can participate.
  • Michael Bradlee will join Leo Pollock, one of the founders of The Compost Plant,  and some surprise guests for a discussion of where RI is going.  Speakers will offer their perspectives on how the industry is progressing in Rhode Island and what some of the obstacles and opportunities are.   This is also an excellent opportunity for others to share what they are seeing in RI as the speakers are just to get the ball rolling.
  • We are also still trying to add a speaker from one of the anaerobic digesters being built in Rhode Island

The focus at lunch time will be the annual trade show.  Exhibitors include:

  • Buxton Hollow Farm
  • Earth Appliance
  • ecoRI News
  • EJ Prescott/Filtrexx
  • O2 compost
  • Rhody Worms Cooperative
  • URI extension
  • The Wormladies of Charlestown

There is still room for additional exhibitors.

The day will end with a panel of Christine Beiling of USEPA, Michael McGonagle of RI Resource Recovery Corporation and Christopher Shafer of RI Department of Environmental Management.

This panel will focus on what our government agencies are doing to reduce food waste and where this is heading from the government’s perspective,.

Information and registration are available at http://www.environmentcouncilri.org/content/2016-compost-conference-trade-show   Admission is $35 including lunch Questions can be answered if you call the ECRI office at 401-621-8048 or email environmentcouncil@earthlink.net